Project Duration
Stipulated Date of Commencement August 02 2003
Actual Date of Completion June 30 2005
Status
100%
Completed
Cost (₹)
Estimated at ₹ 42,004,000.00
Awarded for ₹ 39,063,000.00
Final Cost of Project ₹ 51,060,946.00

Project highlights

The work involved improving the riding quality by providing bituminous layer.

 
Contractors
M/s. Sudin N. Verenker, M/s. Sudin N. Verenker
Consultants
M/s. S. N. Bhobe & Associates Pvt. Ltd
 