Status
100%
Completed
Project highlights
Construction of Bus stand having provison of 10 parking bay for buses, 4 commercial shops and other facilities. A mutipurpose hall with seating capacity of 800 with stage and changing rooms is attached to the Bus stand.
Sub Works
This project involved 5 sub works. The details of the same available below
1
Phase I : Land Development.
100% completed
Project Duration
Stipulated Date of Commencement
November 06 2008
Stipulated Date of Completion /
Likely Date of Completion March 05 2009
Likely Date of Completion March 05 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,891,687.00
Awarded for
₹ 7,300,000.00
Final Cost of Project
₹ 4,623,023.00
Contractors
M/s. Rohit Equipments
Consultants
M/s. Rahul Deshpande & Associates
2
Civil & Electrical works
100% completed
Project Duration
Stipulated Date of Commencement
November 25 2010
Stipulated Date of Completion /
Likely Date of Completion March 11 2013
Likely Date of Completion March 11 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,07,10,082.00
Awarded for
₹ 6,22,69,573.00
Final Cost of Project
₹ 86,264,969.00
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Rahul Deshpande & Associates
3
HVAC work.
100% completed
Project Duration
Stipulated Date of Commencement
March 25 2012
Stipulated Date of Completion /
Likely Date of Completion December 12 2013
Likely Date of Completion December 12 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,420,639.00
Awarded for
₹ 3,539,999.00
Project highlights
Air conditioning works for Multipurpose hall
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
4
Acoustic work for Multipurpose Hall.
100% completed
Project Duration
Stipulated Date of Commencement
May 06 2012
Stipulated Date of Completion /
Likely Date of Completion April 13 2013
Likely Date of Completion April 13 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,551,260.00
Awarded for
₹ 7,326,587.00
Final Cost of Project
₹ 6,778,285.00
Project highlights
Acoustic works for Multipurpose hall
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rahul Deshpande & Associates
5
External Electrical Work
100% completed
Project Duration
Stipulated Date of Commencement
January 14 2013
Stipulated Date of Completion /
Likely Date of Completion December 12 2013
Likely Date of Completion December 12 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,848,415.93
Awarded for
₹ 4,426,921.55
Project highlights
External Electrical Work
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Resurfacing of main road from Miramar Circle to NIO Circle for IFFI 2012.
View ProjectDesign and Construction of Grade Separator at Dabolim Airport.
View ProjectConstruction of Jetty at Brittona – Additional electrical works
View Project