Status
100%
Completed

Project highlights

Construction of Bus stand having provison of 10 parking bay for buses, 4 commercial shops and other facilities. A mutipurpose hall with seating capacity of 800 with stage and changing rooms is attached to the Bus stand.

 
 

Sub Works

This project involved 5 sub works. The details of the same available below

1

Phase I : Land Development.

100% completed
 
Project Duration
Stipulated Date of Commencement November 06 2008
Stipulated Date of Completion /
Likely Date of Completion
March 05 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,891,687.00
Awarded for ₹ 7,300,000.00
Final Cost of Project ₹ 4,623,023.00
 
Contractors
M/s. Rohit Equipments
Consultants
M/s. Rahul Deshpande & Associates
2

Civil & Electrical works

100% completed
 
Project Duration
Stipulated Date of Commencement November 25 2010
Stipulated Date of Completion /
Likely Date of Completion
March 11 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,07,10,082.00
Awarded for ₹ 6,22,69,573.00
Final Cost of Project ₹ 86,264,969.00
 
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Rahul Deshpande & Associates
3

HVAC work.

100% completed
 
Project Duration
Stipulated Date of Commencement March 25 2012
Stipulated Date of Completion /
Likely Date of Completion
December 12 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,420,639.00
Awarded for ₹ 3,539,999.00

Project highlights

Air conditioning works for Multipurpose hall

 
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
4

Acoustic work for Multipurpose Hall.

100% completed
 
Project Duration
Stipulated Date of Commencement May 06 2012
Stipulated Date of Completion /
Likely Date of Completion
April 13 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,551,260.00
Awarded for ₹ 7,326,587.00
Final Cost of Project ₹ 6,778,285.00

Project highlights

Acoustic works for Multipurpose hall

 
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rahul Deshpande & Associates
5

External Electrical Work

100% completed
 
Project Duration
Stipulated Date of Commencement January 14 2013
Stipulated Date of Completion /
Likely Date of Completion
December 12 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,848,415.93
Awarded for ₹ 4,426,921.55

Project highlights

External Electrical Work

 
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates

See Similar Projects

Resurfacing of main road from Miramar Circle to NIO Circle for IFFI 2012.

View Project

Design and Construction of Grade Separator at Dabolim Airport.

View Project

Construction of Jetty at Brittona – Additional electrical works

View Project
x