Project Duration
Stipulated Date of Commencement May 07 2014
Actual Date of Completion July 26 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,057,180.00
Awarded for ₹ 1,142,198.72
Final Cost of Project ₹ 1,556,693.39

Project highlights

Demolition of old dilipidated structures

 
Contractors
M/s. R.S.Lawande
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.
 