Project Duration
Stipulated Date of Commencement
July 01 2015
Actual Date of Completion
August 29 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,448,187.00
Awarded for
₹ 3,317,873.00
Final Cost of Project
₹ 3,013,363.00
Project highlights
Supply of hospital furnitures for new burns ward at GMC
Contractors
M/s. Royal Safe Company (KB)
Consultants
Inhouse