Project Duration
Stipulated Date of Commencement
December 25 2010
Stipulated Date of Completion /
Likely Date of Completion April 24 2011
Likely Date of Completion April 24 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,26,16,252.00
Awarded for
₹ 1,29,52,000.00
Contractors
M/s. Mediconz International
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Supply Installation Testing & Commissioning of Geysers & Water Purifiers.
View Project
Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa. SH : Maintenance of Split, Window Type, Mega split, Multi split and Tower type Air Conditioners installed in GMC Complex, Bambolim (2020-2023)
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Emerson make 40 KVA UPS system installed at Goa Medical College for three years
View Project