Project Duration
Stipulated Date of Commencement
December 25 2010
Stipulated Date of Completion /
Likely Date of Completion April 24 2011
Likely Date of Completion April 24 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,26,16,252.00
Awarded for
₹ 1,29,52,000.00
Contractors
M/s. Mediconz International
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.