Project Duration
Stipulated Date of Commencement
November 05 2018
Stipulated Date of Completion /
Likely Date of Completion May 26 2018
Likely Date of Completion May 26 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 111,150.00
Awarded for
₹ 114,690.00
Contractors
M/s.Vask Traders
Consultants
In-house (GSIDC)