Project Duration
Stipulated Date of Commencement December 30 2016
Actual Date of Completion February 28 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,57,38,286.00
Awarded for ₹ 8,40,52,610.00
Final Cost of Project ₹ 90,390,541.00

Project highlights

Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works.

 
Contractors
M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd
Consultants
M/s LKS India Pvt. Ltd.
 