Project Duration
Stipulated Date of Commencement
November 15 2010
Stipulated Date of Completion /
Likely Date of Completion March 14 2011
Likely Date of Completion March 14 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,148,451.00
Awarded for
₹ 18,422,874.33
Contractors
M/s. Knchan Associates
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
See Similar Projects
Audio-Video Works
View Project
INTERIOR WORKS
View Project
Restoration of Fonte Fenix, spring at Mala Panaji.
View Project





