Project Duration
Stipulated Date of Commencement
July 03 2010
Stipulated Date of Completion /
Likely Date of Completion October 02 2010
Likely Date of Completion October 02 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,268,800.00
Awarded for
₹ 2,741,000.00
Contractors
M/s. James Electrical
Consultants
M/s. Vijaykumar Sawant Associates