Project Duration
Stipulated Date of Commencement
December 30 2016
Stipulated Date of Completion /
Likely Date of Completion March 30 2017
Likely Date of Completion March 30 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,57,38,286.00
Awarded for
₹ 8,40,52,610.00
Project highlights
Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s LKS India Pvt. Ltd.