Project Duration
Stipulated Date of Commencement
March 26 2007
Actual Date of Completion
July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,420,363.00
Awarded for
₹ 8,520,325.00
Contractors
M/s. Lit Homes
Consultants
M/s. Effective Architectural Services