Project Duration
Stipulated Date of Commencement
November 14 2021
Stipulated Date of Completion /
Likely Date of Completion January 13 2022
Likely Date of Completion January 13 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,061,602.01
Awarded for
₹ 1,156,969.00
Project highlights
Interior work for Panchayat building

Contractors
M/S. Creation Interior Contractors

Consultants
M/s. Datta Kare Associate