Project Duration
Stipulated Date of Commencement
April 14 2013
Stipulated Date of Completion /
Likely Date of Completion June 13 2013
Likely Date of Completion June 13 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,534,470.00
Awarded for
₹ 2,038,389.00
Project highlights
All types of Signages works.
Contractors
M/s. Sai Shilp
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.