Project Duration
Stipulated Date of Commencement January 03 2014
Stipulated Date of Completion /
Likely Date of Completion
March 03 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 367,500.00
Awarded for ₹ 388,500.00
 
Gallery Image
Contractors
M/s. B L Lifesciences Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.

View Project
Similar Project

Electrical Works.

View Project
Similar Project

Minor maintenance works at Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.