Project Duration
Stipulated Date of Commencement
December 30 2005
Stipulated Date of Completion /
Likely Date of Completion April 30 2006
Likely Date of Completion April 30 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,970,000.00
Awarded for
₹ 1,793,000.00
Contractors
M/s. Schindler (I) Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates