Project Duration
Stipulated Date of Commencement
November 03 2010
Stipulated Date of Completion /
Likely Date of Completion October 06 2010
Likely Date of Completion October 06 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,450,378.00
Awarded for
₹ 7,290,025.00
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.