Project Duration
Stipulated Date of Commencement
September 29 2013
Actual Date of Completion
August 14 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 145,763,468.00
Awarded for
₹ 158,936,223.00
Final Cost of Project
₹ 118,295,800.50
Project highlights
• Total built-up area = 3610.63 sq. m.
• Ground Floor : Admin office, staff, etc.
• First Floor : 2 lecture halls.
• Second Floor : 1 lecture hall.
• Other facilities such as lift, fire fighting, HVAC, seat & desk with self opening & closing system.
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 1 sub works. The details of the same available below
1
Furniture and Acoustical work.
100% completed
Project Duration
Stipulated Date of Commencement
May 22 2015
Stipulated Date of Completion /
Likely Date of Completion August 14 2015
Likely Date of Completion August 14 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,386,310.00
Awarded for
₹ 10,777,777.00
Final Cost of Project
₹ 9,607,181.00
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Construction of Government College of Commerce & Economics at Margao, Goa – Civil, plumbing, electrical, lift and fire fighting – Phase I.
View ProjectProviding of split air conditioners.
View ProjectFurnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka
View Project