Project Duration
Stipulated Date of Commencement
December 19 2009
Stipulated Date of Completion /
Likely Date of Completion August 18 2010
Likely Date of Completion August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,042,857.00
Awarded for
₹ 14,820,456.00
Contractors
M/s. Imperial Engineering Company
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for 4 nos. of Emerson make 30 KVA UPS systems installed for Modular OTs 1-4 at Goa Medical College and Hospital, Bambolim for six months
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance Contract for ten numbers of UPS installed at Sub District Hospital, Ponda for three years
View Project
Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim – Goa -SH-Supply, Installation, Testing and Commissioning of Ventilators
View Project