Project Duration
Stipulated Date of Commencement
April 26 2008
Stipulated Date of Completion /
Likely Date of Completion July 25 2008
Likely Date of Completion July 25 2008
Status
100%
Completed
Cost (₹)
Awarded for
₹ 11,258,858.00
Contractors
M/s. Royal Safe Company
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Supply, Installation, Testing and Commissioning of negative pressure VRDL lab at Goa Medical College and Hospital, Bambolim.
View Project
Construction of IInd phase of Goa Dental College & Hospital at Bambolim, Goa-Civil,Plumbing, internal electrical and fire fighting works-Balance work.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa