Likely Date of Completion September 20 2009
Project highlights
• Total built-up area: 6191.62 sq. m.
• Building consists of basement, ground floor and first floor
• Total no. of beds: 86 nos. [General Ward – Male : 20 nos., General Ward – Female : 20 nos., General Ward – Gynecology : 20 nos., Neonatal ward: 20 nos., Special Rooms (6 nos): 6 beds.
• Total no. of Operation Theatres: 02.
• 4 body Mortuary Cabinet : 01 no.
• Facilities provided:
• Basement (Area: 1095.76 sq.mts) : Canteen, equipment / store room, hospital store, electrical room, CSSD, changing rooms for gents & ladies staff, morgue, garbage collection, toilet facilities.
• Ground Floor (Area: 2558.21 sq.mts) : General ward (female), general ward (male), general ward (gynaecology) with nurses’ rooms & attached toilet blocks, 6 special rooms, linen store rooms for each ward, ultrasound, treatment room, examination room, x-ray, dark room, doctor’s room, ECG room, reception counter, waiting area & toilet facilities.
• First Floor (Area: 2537.65 sq.mts) : Registration counter, ENT, DOTS centre, skin specialist, general medicine store, pharmacy, waiting area, procedure room, immunization, dental, physiotherapist, pathologist room, laboratory, sample distribution & sample collection room, cabins for health officer & medical officer, administration block, neonatal ward with nurses room, cabin for neonatologist, sanitary inspector room, operation theatres, hall for anganwadi meetings & toilet facilities.
• Building is provided with lift, connecting ramps, air conditioning and medical gases facilities.
![Gallery Image](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Gallery Image](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
Sub Works
This project involved 8 sub works. The details of the same available below
Lift work.
Likely Date of Completion August 18 2010
Project highlights
Lift work.
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
Electrical & Fire Fighting work.
Likely Date of Completion January 15 2011
Project highlights
Electrical & Fire Fighting work.
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
Air Conditioning work
Likely Date of Completion March 24 2011
Project highlights
Air Conditioning work
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
False ceiling works.
Likely Date of Completion January 01 2011
Project highlights
False ceiling works
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
STP & ETP works
Likely Date of Completion September 09 2011
Project highlights
Sewage and effluent treatment facility
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
Medical Gas & Steel OT work.
Likely Date of Completion January 03 2012
Project highlights
Medical Gas & Steel OT work.
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
Furniture works.
Likely Date of Completion August 03 2013
Project highlights
Furniture works
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
Motruary Cabinet Works
Likely Date of Completion May 20 2013
Project highlights
Motruary Cabinet Works
![Contractors](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon07.png)
Contractors
![Consultants](https://www.gsidcltd.com/wp-content/themes/gsidc/images/icon08.png)
Consultants
![Similar Projects](https://www.gsidcltd.com/wp-content/themes/gsidc/images/banner10.jpg)
See Similar Projects
![Similar Project](https://www.gsidcltd.com/wp-content/themes/gsidc/images/similarProject03.jpg)
Medical Gas & Steel OT work.
View Project![Similar Project](https://www.gsidcltd.com/wp-content/themes/gsidc/images/similarProject03.jpg)
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – S.H- Maintenance /Renovation work of Community Health Center at Canacona – Maintenance Contract for Schindler Elevator installed at Canacona CHC
View Project![Similar Project](https://www.gsidcltd.com/wp-content/themes/gsidc/images/similarProject03.jpg)
Power upgradation works (Phase I) for GMC Complex and Nurses’ College Campus, Bambolim, Goa.
View Project