Project Duration
Stipulated Date of Commencement
September 06 2018
Stipulated Date of Completion /
Likely Date of Completion December 07 2018
Likely Date of Completion December 07 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1.17 cr
Awarded for
₹ 0.98 cr
Project highlights
Strengthening of FDA laboratories, Bambolim Goa
Contractors
M/s. Bioxia
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD