Project Duration
Stipulated Date of Commencement
August 30 2018
Stipulated Date of Completion /
Likely Date of Completion September 08 2019
Likely Date of Completion September 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 170,155,916.00
Awarded for
₹ 174,845,805.00
Project highlights
Interior & furniture works
Contractors
M/s. Jayant K. Furnishers
Consultants
M/s. Rajesh Kenkre