Project Duration
Stipulated Date of Commencement
January 14 2021
Stipulated Date of Completion /
Likely Date of Completion April 23 2021
Likely Date of Completion April 23 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,161,784.00
Awarded for
₹ 3,463,206.00
Project highlights
Repair works
Contractors
M/S. Race Constructions
Consultants
M/s. Rahul Deshpande and Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Repairs & Upgradation of Solid Waste Management Facilities within the Jurisdiction of CCP in Panaji City – Electrical Works.
100% completed
Project Duration
Stipulated Date of Commencement
June 20 2021
Stipulated Date of Completion /
Likely Date of Completion October 17 2021
Likely Date of Completion October 17 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,658,751.00
Awarded for
₹ 11,264,964.00
Project highlights
Electrical wiring, SITC of electrical substation at three existing sheds
1) Organic waste management facility behind Heera petrol pump patto.
2) Waste Management facility opposite LIC building at Patto.
3) Material recovery facility at St. Inez in panaji.
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
False ceiling, interior, furniture, signage, security installation and other miscellaneous works.
View Project
Additional miscellaneous works
View Project
Cortalim to Verna via Airport – 24.00 km.
View Project





