Project Duration
Stipulated Date of Commencement
May 29 2015
Actual Date of Completion
March 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,635,824.00
Awarded for
₹ 12,954,011.47
Final Cost of Project
₹ 11,301,595.00
Project highlights
• Total built-up area : 400 sq. m.
• Conference Room.
• Director and Deputy Director’s Cabin.
• Work Stations for Staff.
• Server Room
Contractors
M/s. Vector Projects India Pvt. Ltd.
Consultants
M/s. Nilesh Salkar Associates