Project Duration
Stipulated Date of Commencement
January 13 2013
Stipulated Date of Completion /
Likely Date of Completion March 12 2013
Likely Date of Completion March 12 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,67,16,761.10
Awarded for
₹ 1,64,23,070.00
Contractors
M/s. Steel Case
Consultants
M/s. Effective Architectural Services