Project Duration
Stipulated Date of Commencement
September 07 2018
Actual Date of Completion
November 22 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,605,962.41
Awarded for
₹ 97,86,999.00
Final Cost of Project
₹ 9,786,999.00
Project highlights
up- gradation of the existing Laboratory facilities
Contractors
M/s. Bioxia
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.