Project Duration
Stipulated Date of Commencement September 07 2018
Actual Date of Completion November 22 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,605,962.41
Awarded for ₹ 97,86,999.00
Final Cost of Project ₹ 9,786,999.00

Project highlights

up- gradation of the existing Laboratory facilities

 
Contractors
M/s. Bioxia
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 