Project Duration
Stipulated Date of Commencement
May 19 2018
Actual Date of Completion
November 18 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,819,379.01
Final Cost of Project
₹ 2,232,171.49
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s Deepak Marathe
Consultants
M/s Vaishali Pednekar Associates (PMC)