Project Duration
Stipulated Date of Commencement
February 23 2007
Stipulated Date of Completion /
Likely Date of Completion September 14 2007
Likely Date of Completion September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,158,850.00
Awarded for
₹ 4,838,400.00
Project highlights
Soft landscaping work comprises of soil development with lawns, foliage & flowering trees, palms, shrubs, ground covers, etc.
Contractors
M/s. Hariyalee Nursery
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – SH: Reprogramming of Audio Video System installed at Sub-District Hospital, Ponda – Goa.
View Project
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Dialysis Machine
View Project
Rural Medical Dispensary at Keri.
View Project