Project Duration
Stipulated Date of Commencement February 23 2007
Stipulated Date of Completion /
Likely Date of Completion
September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,158,850.00
Awarded for ₹ 4,838,400.00

Project highlights

Soft landscaping work comprises of soil development with lawns, foliage & flowering trees, palms, shrubs, ground covers, etc.

 
Gallery Image
Contractors
M/s. Hariyalee Nursery
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing, commissioning of fire detection and alarm system

View Project
Similar Project

Maintenance contract for 8 Nos. of elevators installed at North Goa District Hospital Mapusa for 3 years

View Project
Similar Project

Additional Miscellaneous Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.