Project Duration
Stipulated Date of Commencement
October 04 2007
Actual Date of Completion
September 30 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,176,740.00
Awarded for
₹ 5,189,889.00
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.