Project Duration
Stipulated Date of Commencement October 04 2007
Stipulated Date of Completion /
Likely Date of Completion
January 03 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,176,740.00
Awarded for ₹ 5,189,889.00
 
Gallery Image
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of IInd Phase of Goa Dental College and Hospital at Bambolim, Goa – Furniture, Interior & Miscellaneous Works.

View Project
Similar Project

Landscape work

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Emerson make 40 KVA UPS system installed at Goa Medical College for three years

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.