Project Duration
Stipulated Date of Commencement June 24 2022
Stipulated Date of Completion /
Likely Date of Completion
November 23 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,066,766.80
Awarded for ₹ 13,903,408.51

Project highlights

Additional internal and external works in the new CHC premises

 
Gallery Image
Contractors
M/s. Sri Srinath Infra
Gallery Image
Consultants
M/s. Saolapurkar and Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of IInd phase at Goa Dental College and Hospital at Bambolilm, Goa -Civil,Plumbing, internal electrical and fire fighting works-

View Project
Similar Project

Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa

View Project
Similar Project

Full renovation and part construction of the old Asilo Hospital for State Health Training Institute at Mapusa-SH-Interior works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.