Status
100%
Completed
Sub Works
This project involved 3 sub works. The details of the same available below
1
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa – Civil and plumbing works.
100% completed
Project Duration
Stipulated Date of Commencement
January 28 2013
Stipulated Date of Completion /
Likely Date of Completion February 28 2014
Likely Date of Completion February 28 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,00,41,753.00
Awarded for
₹ 3,90,22,573.00
Final Cost of Project
₹ 65,294,397.00
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2
Electrical Works.
100% completed
Project Duration
Stipulated Date of Commencement
May 26 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2014
Likely Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,50,771.00
Awarded for
₹ 23,88,737.00
Contractors
M/s. Mohan Electricals
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
3
HVAC Works.
100% completed
Project Duration
Stipulated Date of Commencement
September 26 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2014
Likely Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,324,109.94
Awarded for
₹ 5,899,999.00
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
False ceiling work.