Project Duration
Stipulated Date of Commencement
October 16 2015
Stipulated Date of Completion /
Likely Date of Completion April 15 2017
Likely Date of Completion April 15 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,848,685.00
Awarded for
₹ 3,502,017.00
Project highlights
Repair & restoration of the spring including walls, tunnels & disilting work.
Contractors
M/s. Kamalakant Amonkar
Consultants
M/s. Ketak Nachnolkar
See Similar Projects
Construction of Multipurpose Hall and office building for Village Panchayat, Salvador do Mundo – Phase I Land Development.
View Project
Development of Open space near Palmar Apartment
View Project
Specialized hand painted tile cladding work
View Project





