Project Duration
Stipulated Date of Commencement
October 10 2008
Stipulated Date of Completion /
Likely Date of Completion May 12 2008
Likely Date of Completion May 12 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,79,387.00
Awarded for
₹ 36,14,544.00

Contractors
M/s. Japsin Wire Drawing Pvt. Ltd.

Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.