Project Duration
Stipulated Date of Commencement August 14 2016
Actual Date of Completion August 15 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,168,164.07
Awarded for ₹ 15,901,572.33

Project highlights

Lower Ground Floor and Ground Floor: 11 shops &
First Floor: Hall along with dining

 
Contractors
M/s. Satish R. Lal
Consultants
M/s. Bhaskar Wagle & Associates
 