Project Duration
Stipulated Date of Commencement
December 26 2014
Stipulated Date of Completion /
Likely Date of Completion May 25 2015
Likely Date of Completion May 25 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,511,233.60
Awarded for
₹ 10,718,701.97
Project highlights
Landscpaing work and garden development
Contractors
M/s. Abhiyant Realty
Consultants
M/s. Nitin Arolkar