Project Duration
Stipulated Date of Commencement
February 08 2019
Stipulated Date of Completion /
Likely Date of Completion November 21 2019
Likely Date of Completion November 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,543,158.00
Awarded for
₹ 10,992,111.60
Project highlights
Repair/Upgrdation works of schools which includes roofing , tiling,dadoes,painting etc.
Contractors
M/s.Sushant Khedekar
Consultants
M/s.Bhaskar Wagle & Associates
See Similar Projects
Repairs/Upgradation & maintenance of Government Schools in State of Goa – Civil, Plumbing & Electrical works – Package G (Quepem Taluka) – GPS Corla, GPMS Kanibag
View Project
Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Fire Fighting work
View Project
Repairs & Upgradation of Government Higher Secondary School Sanquelim.
View Project





