Project Duration
Stipulated Date of Commencement March 03 2014
Actual Date of Completion April 22 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,095,133.00
Awarded for ₹ 11,567,161.27
Final Cost of Project ₹ 12,512,670.00

Project highlights

Repairs & Upgradation of Government Higher Secondary Sanquelim

 
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Bhaskar Wagle & Associates
 