Project Duration
Stipulated Date of Commencement
March 03 2014
Stipulated Date of Completion /
Likely Date of Completion February 09 2014
Likely Date of Completion February 09 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,095,133.00
Awarded for
₹ 11,567,161.27
Project highlights
Repairs & Upgradation of Government Higher Secondary Sanquelim
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Bhaskar Wagle & Associates