Project Duration
Stipulated Date of Commencement
March 04 2014
Stipulated Date of Completion /
Likely Date of Completion May 03 2014
Likely Date of Completion May 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,664,951.00
Awarded for
₹ 3,327,405.00
Project highlights
Fire Fighting work
Contractors
M/s. Suchi Turnkey Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.
See Similar Projects
Reconstruction of Government Primary School at Vithalapur in Sankhali, Bicholim Taluka -Furniture works
View Project
Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa -HVAC work
View Project
Infrastructure works for Sanjay Centre for Special Education at Porvorim
View Project





