Project Duration
Stipulated Date of Commencement
March 01 2019
Stipulated Date of Completion /
Likely Date of Completion June 29 2019
Likely Date of Completion June 29 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,461,990.00
Awarded for
₹ 5,800,069.00
Project highlights
interior & Miscellaneous works in Administration Block
Contractors
M/S.Creation Interior Contractor
Consultants
M/s. F P Project Management Pvt. Ltd.