Project Duration
Stipulated Date of Commencement March 04 2014
Actual Date of Completion February 20 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,000,000.00
Awarded for ₹ 5,000,000.00
Final Cost of Project ₹ 7,522,446.00

Project highlights

Repairs and renovation of roofing, to 06 number of Government Primary schools in Canacona Taluka in this package.

 
Contractors
M/s K G Thomas
Consultants
M/s Manoj Amshekar
 