Project Duration
Stipulated Date of Commencement
November 30 2019
Stipulated Date of Completion /
Likely Date of Completion November 08 2020
Likely Date of Completion November 08 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,768,360.00
Awarded for
₹ 11,437,653.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Neha Eleccon Services Pvt. Ltd
Consultants
M/s. Nitin Arolkar
See Similar Projects
Construction of Ashram school under Centrally sponsored scheme of Ministry of Tribal affaires at Moshiphond in the Village Ponguinim of Canacona Taluka.
View Project
Construction of Anganwadi Centres from NABARD Assistance.
View Project
Extension of H. B. Government High School at Thane in Sattari Taluka.
View Project