Project Duration
Stipulated Date of Commencement
November 30 2019
Stipulated Date of Completion /
Likely Date of Completion November 08 2020
Likely Date of Completion November 08 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,768,360.00
Awarded for
₹ 11,437,653.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Neha Eleccon Services Pvt. Ltd
Consultants
M/s. Nitin Arolkar
See Similar Projects
Renovation of Building No.4, Lyceum Complex, Altinho, Panaji.- Civil Works
View Project
Repairs/Upgradation & Maintenance Of Government Schools In The State Of Goa: (GPS Akarwada Priol, GPS Apewal Priol, GPS Galwada Priol, GPS Khananwada Priol, GPS Magilwada Priol. (Ponda Taluka)
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Pernem Taluka: Package – V (GPS Tiwade Dhargal, GPS Chandel, GPS Madkai Ozari, GPS Varkhand, GPS Bhatpavni, GPS Patradevi, GPS Fakirpata Torse, GPS Tulaskarwadi)
View Project