Project Duration
Stipulated Date of Commencement February 14 2019
Stipulated Date of Completion /
Likely Date of Completion
August 28 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,765,344.00
Awarded for ₹ 6,453,546.81

Project highlights

Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka