Project Duration
Stipulated Date of Commencement
September 05 2018
Stipulated Date of Completion /
Likely Date of Completion May 19 2019
Likely Date of Completion May 19 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,400,666.00
Awarded for
₹ 9,172,221.87
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Shri Hari Krishna Constructions