Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion October 15 2019
Likely Date of Completion October 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,042,722.21
Awarded for
₹ 13,503,700.00
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Bhaskar Wagle and Associates.