Project Duration
Stipulated Date of Commencement
August 03 2018
Stipulated Date of Completion /
Likely Date of Completion July 03 2019
Likely Date of Completion July 03 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,726,550.06
Awarded for
₹ 16,166,241.78
Project highlights
Repairs/ upgradation of schools which include proviison of new double skin galvalum sheet roofing, tiling, painting etc.
Contractors
M/s.A.Y Gulumkar
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Civil, Plumbing & Electrical works.