Project Duration
Stipulated Date of Commencement December 27 2013
Actual Date of Completion January 20 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 73,214,248.00
Awarded for ₹ 85,526,271.00
Final Cost of Project ₹ 80,741,743.00
 
Contractors
M/s. R. B. S. Candiaparcar
Consultants
M/s. Datta Kare Associates
 