Project Duration
Stipulated Date of Commencement
December 27 2013
Stipulated Date of Completion /
Likely Date of Completion January 08 2015
Likely Date of Completion January 08 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,214,248.00
Awarded for
₹ 85,526,271.00
Contractors
M/s. R. B. S. Candiaparcar
Consultants
M/s. Datta Kare Associates