Project Duration
Stipulated Date of Commencement
July 01 2016
Stipulated Date of Completion /
Likely Date of Completion June 30 2017
Likely Date of Completion June 30 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 37,611,190.00
Awarded for
₹ 36,323,784.00