Project Duration
Stipulated Date of Commencement December 01 2018
Actual Date of Completion September 30 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,149,290.00
Awarded for ₹ 9,601,950.00
Final Cost of Project ₹ 5,347,151.25

Project highlights

construction of compound wall around the plot boundry

 
Contractors
M/s. Race Constructions
Consultants
M/s. Ulysis
 