Project Duration
Stipulated Date of Commencement
April 04 2018
Stipulated Date of Completion /
Likely Date of Completion March 07 2018
Likely Date of Completion March 07 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,004,938.00
Awarded for
₹ 944,596.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.A Y Gulumkar
Consultants
M/s.Nitin Arolkar
See Similar Projects
Construction of Anganwadi Centres from NABARD Assistance – Package III (GPS Pernem, GPS Mandrem, GPS Korgao).
View Project
Reconstruction of school at GPS Bicholim (Central)
View Project
Lifts / Elevator work.
View Project





