Project Duration
Stipulated Date of Commencement
March 11 2016
Stipulated Date of Completion /
Likely Date of Completion February 07 2017
Likely Date of Completion February 07 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,739,626.24
Awarded for
₹ 15,306,382.50
Project highlights
School Building with 4 classrooms of international size along other basic aminities .
Contractors
M/s.Riffaath Constrctions
Consultants
M/s.Datta Kare Associates